|
All images may be clicked
for enlargement.
Day 1 Before the deck can get underway,
the Top Deck Decking Builders Ltd, prepare for the treated timber sub-frame. As
the deck is to be built on a very steep bank, extra care had to be taken with
the siting and strength of the sub deck frame.

The first stage undertaken her with
the large raised deck, was to get the upright support posts concreted
into the ground to a suitable depth to allow for any 'made up' ground on
the bank. This bank has been well consolidated over many years, so was
able to take the posts for the large deck, without huge holes being dug
out.
The decking system to be used called
for the installation of a double bearer, positioned so that it allowed
for the maximum 900m overhang for the raised deck front edge. Just three
posts were inserted in the first instance to allow the fixing of the
bearer joists at the correct level for the joists of the deck that would
rest upon it. Additional posts were then added once the double joist
bearer had been levelled and fixed. The dimensions of the bearer timbers
being 150x50mm (6x2in)


Day 2
Once the bearer was fixed and additional
support posts inserted, the placing of the decking joists was much the
same as for any raised deck. Again. 150x50mm joists were used at 600
spacing. At the house end of things, the joists simply slotted into
joist hangers on the wall plate that had been fixed. If there seems to
be lack of detail on the finer points, it is simply because this is not
meant to be a DIY manual on how to build a large raised deck. If you
have the experience, then you should be able to see the procedure for
this raised deck quite easily.
Once the decking sub frame was completed,
the upright newels for the balustrades were fixed.

Day3

Day 5 & 6 (Rained off on Day 4)

Day 7 - Job done!

 |